TM 10-3930-242-12
STEP 1:
CAREFULLY DRIVE UP TO POSITIO WHERE LOAD IS TO BE DEPOSITED.
STEP 2:
DEPRESS INCHING PEDAL.
PUSH FORK EXTENSION CONTROL LEVER FORWARD TO EXTEND FORKS
STEP 3:
LONGITUDINALLY.
PUSH FORK TILT CONTROL LEVER FORWARD TO TILT CARRIAGE TO VERTICAL POSITION.
STEP 4:
STEP 5:
IF LOAD IS TO BE DEPOSITED ON GROUND LEVEL, PUSH FORK LIFT CONTROL LEVER
FORWARD AND ALLOW LOAD TO LOWER SLOWLY TO RESTING PLACE. CONTINUE TO
LOWER FORKS UNTIL THEY CAN BE EASILY WITHDRAWN FROM PALLET. THEN PROCEED
WITH STEP 10.
STEP 6:
IF LOAD IS TO BE DEPOSITED ON A TIERED STACK, PULL FORK LIFT CONTROL LEVER
BACK UNTIL LOAD REACHES DESIRED HEIGHT ABOVE TIER, THEN PROCEED WITH STEPS
7 THROUGH 10.
STEP 7:
RELEASE INCHING PEDAL ABOUT HALFWAY AND INCH TRUCK FORWARD UNTIL LOAD IS
ABOVE ITS RESTING PLACE.
STEP 8:
DEPRESS 'INCHING PEDAL.
STEP 9:
PUSH FORK LIFT CONTROL LEVER FORWARD AND LOWER LOAD CAREFULLY TO ITS
RESTING PLACE. CONTINUE TO LOWER FORKS UNTIL THEY CAN BE EASILY WITHDRAWN
FROM PALLET.
STEP 10:
PLACE FWD-NEUT-REV CONTROL LEVER IN REV AND RELEASE INCHING PEDAL.
TA072391
Figure 2-8. Depositing load.
2-10
|