TM 10-3930-673-20-2
16
This Task Covers:
a. Removal
a.1 Cleaning and Lubricating
b. Installation
INITIAL SETUP
Materials/Parts
Tools and Special Tools
Compound, Sealing (Item 30, Appendix C)
Tool Kit, General Mechanic's: Automotive
Lubricant, Teflon, Dry (Item 15.1, Appendix C)
(Item 18, Appendix F)
Brush, Nylon, Bristle
Lifting Device, 5 ton (4535.92 kg) capacity
Personnel Required
Equipment Condition
Two
Wheels chocked
References
TM 10-3930-673-10
a. Removal.
TR00003
WARNING
When working under boom, always use
blocks, jackstands or other rigid and
stable supports. Combined weight of
boom and attachment is approximately
TR00504
6300 lb (2857.63 kg). Failure to
adequately support boom could result in
severe injury or death to personnel.
NOTE
Both 6K and 10K carriage left and right
forks are removed and installed the same
way.
(1)
Position forks (1) flat and just resting on
ground (TM 10-3930-673-10).
(2)
Remove two screws (2) and retaining plate
(3) from carriage (4).