BOOM CYLINDER FLOW CONTROL VALVE REPLACEMENT - CONTINUED
0182 00
INSTALLATION
NOTE
Remove caps and plugs as hoses are installed. Wipe all sealing surfaces on valve and hoses clean and dry.
8
8
1.
Connect flow control valve (4) into reducer (5) of
main control valve (6) and tighten securely.
2.
Connect hydraulic hoses (3) as tagged.
3.
Connect hydraulic hose (3) to fitting (7).
4.
Connect hoses (1) and (2) to flow control valve (4).
4
7
5.
Tighten all fittings (8) securely.
1
2
409-4068
3
6.
Install transmission cover (WP 0150 00).
NOTE
It is possible that the hydraulic pumps have air in the pump cavities. This air must be purged from the cavity
before the pump will operate.
7.
Start engine, check for leaks and proper operation (TM 10-3930-660-10).
8.
Purge air from hydraulic circuit by raising and lowering boom five times.
9.
Stop engine and relieve hydraulic pressure by operating boom raise and lower controls (TM 10-3930-660-10).
END OF WORK PACKAGE