NOTE
Be sure new or rebuilt pump is well
oiled prior to installation.
11.
Install the main hydraulic pump on transmission
using a new gasket. Install and tighten pump
mounting bolts to torque spec: 37-41 Ib-ft (50-56
Nm)
Refer to Section 10.3, Main Hydraulic Pump Removal/
Installation.
12. Install the hydraulic lines to main pump. Be sure
the O-ring seals are properly positioned.
Refer to Section 10.0, Main Hydraulic and Steering
Lines.
13. Reconnect the brake lines. See Section 8.4.
14. Tighten brake line tube fittings to torque spec;
135-145 lb-in (15-16 N-m).
NOTE
After installation of transaxle in the
truck, the entire brake system must
be bled to remove all air from the
system according to recommended
brake bleeding procedure. Refer to
Section
8.5,
Brake
Bleeding
Procedures (TA18 transaxle).
15. Install new transmission oil filter.
16. Install the transmission cooling lines to the
transaxle. Be sure they are in the correct
position (refer to the markings placed on them at
removal).
Refer to Section 4.8 Cooling System.
17. Install the power steering lines to the steering
gear (valve). Be sure they are installed to the
correct ports (refer to the markings placed on
them at removal).
Refer to Section 9. , Steering System and Section 10.0,
Main Hydraulic and Steering Lines.
18. Connect the steer valve sump return line at the
sump tank inlet.
19. Install the accelerator linkage, as required.
20. Reconnect the directional control (shift) linkage.
Reconnect wiring leads to control cover solenoid
terminals. Check the markings on them to be
sure each is installed on the correct solenoid.
Refer to Section 7.12, Directional Control Linkage.