TM 10-3930-671-24
STEP 24 Remove the cam ring (Figure 3.24). 3.26b).
FIGURE 3.24.
STEP 25 Check and record the roller to roller dimension
as instructed in Step 3 of reassembly (Figure 5.3).
Compare this dimension with that called for on the pump
specification (Figure 3.25).
FIGURE 3.25.
STEP 26 Using socket head wrench, remove the leaf
spring adjusting screw. Remove the leaf spring (Figure
3.26a). In some cases, a shim is used beneath the leaf
spring to limit the maximum roller to roller dimension to
.005" above the specification. If a shim is present,
remove it at this time. Be sure to reinstall the shim during
the reassembly.
Remove the shoes and rollers from the rotor (Figure
3.2b).
FIGURE 3.26b.
Use pressure regulating sleeve extractor to push the
pumping plungers from their bore. Handle all parts
carefully with clean hands wet with calibrating fluid
(Figure 3.26c).
FIGURE 3.26c..
STEP 27 Lift the rotor from the head (Figure 3.27).
NOTE
Do not handle the precision ground surface of the
rotor.
FIGURE 3.27.
F-230
|