TM 10-3930-669-20
CONTINUITY TEST
(1) Remove engine ventilation panel (Para
6-2).
(2) Disconnect alternator connector from
harness connector.
(3) Ground alternator connector, wire 64
terminal to a known good ground.
(4) Set multimeter select switch to OHMS.
(5) Check continuity between connector
wire 64 terminal and a known good
ground.
(a) If there is no continuity, repair wire
64 (see schematic Appendix F).
(b) If there is continuity, wire 64 is OK.
(6) Connect
alternator
connector
on
harness connector.
(7) Install engine ventilation panel.
CONTINUITY TEST
(1) Disconnect connector from wire 64 and
hour meter wire.
(2) Connect positive (+) multimeter lead to
connector wire 64 terminal.
(3) Connect negative (-) multimeter lead to
connector terminal.
(a) If there is no continuity, replace
connector (Para 7-10).
(b) If
there
is
continuity,
replace
alternator (Para 7-2).
(4) Connect wire 64 and hour meter wire to
connector.
(5) Install instrument panel (Para 7-8).
2-159
|