g.
Load Placement Operating Procedure Using Mast Pivot.
(1)
Approach the rack opening at a slow (creep) speed keeping forklift parallel to rack.
(2)
While approaching the rack opening, raise the load to the proper height.
(3)
While approaching the rack opening, shift the mast assembly slightly to the left of center and begin
pivoting load clockwise towards rack.
NOTE
The load face nearest the operator should be very close to the vertical rack member and in
view of the operator.
You will notice mast assembly clockwise pivot and left-hand shift action at the same time.
These functions will not be synchronized and one function may stop before the other.
(4)
As the right corner of the load clears the rack vertical member, shift the mast assembly farther to the left
and pivot load clockwise toward the rack as much as possible.
2-33
|