TM 10-3930-664-24
12.
CONNECT HOSE ASSEMBLIES (35, 36, 37,
38)
WITH
FITTINGS
TO
INTERMEDIATE
RAIL
MANIFOLD (30).
a.
Install adapter (48) and new O-ring (49)
into intermediate rail manifold (30).
b.
Connect hose assembly (47) to adapter
(48) and bottom of main lift cylinder.
c.
Install adapters (43, 44) and new O-rings
(45, 46) into top of intermediate rail
manifold (30).
d.
Install adapters (39, 40) and new O-rings
(41, 42) into sides of intermediate rail
manifold (30).
e.
Connect hose assemblies (35, 36, 37, 38)
to intermediate rail manifold (30).
13.
CONNECT HOSE ASSEMBLIES (28, 29) WITH
FITTINGS TO ROTATE MANIFOLD (15).
a.
Install fittings (32) into rotate manifold
(15).
b.
Install bulkhead fitting (31) and
bulkhead elbow (33) onto sideshift bracket
(34) using nuts.
c.
Carefully feed hose assemblies (28, 29)
over freelift chain roller.
d.
Connect hose assemblies (28, 29) to
fittings (31, 32) and elbow (33).
2-432
|