TM 10-3930-660-24-1
MAIN CONTROL VALVE MAINTENANCE - CONTINUED
0175 00
ADJUSTMENT OF BOOM HOIST RELIEF VALVE
NOTE
The main relief valve pressure must be adjusted above normal operating pressure to permit the boom hoist
relief valve pressure to be adjusted. Main relief valve pressure is then returned to normal operating pressure
at the end of this procedure.
1.
Remove main relief valve plug (11).
2.
Connect 0 to 5,000 psi (0 to 34474 kPa) pressure gauge to plug port (12).
3.
Remove acorn nut (13) covering slotted head adjusting screw (14).
4.
While holding adjusting screw (14), loosen and back off jamnut (15) which secures adjusting screw.
NOTE
Engine may be operated at idle or full throttle when performing pressure tests.
5.
Start engine (TM 10-3930-660-10).
6.
Operate boom extend, retract, hoist or lower function
until hydraulic oil is passing over relief valve. Con-
tinue to hold hydraulic lever in that position so oil
passes over relief valve during relief valve adjustment.
7.
Turn adjusting screw (14) clockwise (in) until pressure
on gauge reads 3,100 psi (21374 kPa).
12
8.
Release hydraulic function lever.
11
9.
Remove acorn nut (19) covering slotted head adjust-
ing screw (20).
15
10.
While holding adjusting screw (20), loosen and back
13,14
off jamnut (21) which secures adjusting screw.
11.
Operate boom hoist function until boom is fully
raised. Continue to hold boom control lever in position
so hydraulic oil passes over relief valve. Read relief
21
19,20
valve pressure on pressure gauge.
12.
Adjust boom hoist relief valve pressure between 2,950
409-659
to 3,050 psi (20340 to 21029 kPa).
13.
To increase relief pressure, turn adjusting screw (18) clockwise (in). To decrease pressure, turn adjusting screw counter-
clockwise (out).
14.
Hold adjusting screw (20) in position and tighten jamnut (21). Install acorn nut (19).
Perform steps 4 through 13 of Adjustment of Main Relief Valve.
15.
0175 00-7
|