TM10-3930-660-20
18-23.
BOOM CHAIN PULLEYS - REPLACE (Contd)
3.
4.
5.
6.
7.
REMOVE CAPSCREW (5) AND LOCKWASHER
(6). DISCARD LOCKWASHER (6).
REMOVE BOTTOM WEAR PAD FASTENERS ON
INTERMEDIATE BOOM.
Remove capscrews (7), lockwashers (8),
and washers (9) securing bottom wear
pad at front of intermediate boom.
Discard lockwashers (8).
REMOVE PULLEY PIN (10).
REMOVE CHAIN PULLEY (11) AND BUSHINGS
(12).
LUBRICATION FITTING (13), IF
REMOVE
NECESSARY.
1.
2.
INSTALL LUBRICATION FITTING (13), IF
REMOVED .
INSTALL CHAIN PULLEY
BUSHINGS (12) ON THE
THE PULLEY PIN (10).
(11), WITH
BOOM AND INSTALL
Apply Loctite 242 to capscrew (5) as
installed.
3. SECURE PULLEY PIN WITH (NEW)
LOCKWASHER (6) AND CAPSCREW (5).
4. SECURE INTERMEDIATE BOOM BOTTOM WEAR
PAD l
Apply Loctite 242 to threads of
capscrews (7).
Install capscrews (7), new lockwashers
(8), and washers (9) to secure bottom
wear pad at front of intermediate boom.
18-91
|