TM 10-3930-659-34
5-10. TRANSMISSION OIL FEED FLANGE MAINTENANCE.
This task covers:
a.
Removal
d.
Assembly
b.
Disassembly
e
Installation
c
Cleaning and Inspection
INITIAL SETUP:
Equipment Conditions:
Materials/Parts:
· Transmission input seal and bearing removed
Sealing compound (Item 14, Appendix B)
(see paragraph 4-43).
Lubricating oil (Item 38, Appendix B)
Tools/Test Equipment:
Petrolatum (Item 42, Appendix B)
Rags (Item 43, Appendix B)
General mechanic's tool kit (Item 71, Appendix E) Dry cleaning solvent (Item 47, Appendix B)
Depth gage micrometer (Item 27, Appendix E)
Two gaskets
Heat gun (Item 35, Appendix E)
Retaining ring pliers (Item 46, Appendix E)
References:
Arbor press (Item 47, Appendix E)
TM 9-214
Mechanical puller (Item 51, Appendix E)
Torque wrench, 0-175 lb.-ft. (Item 81, Appendix E)
General Safety Instructions:
Air deflector plate (Figure C-6, Appendix C)
Dry cleaning solvent is flammable and must not be
Transmission oil supply flange removal brackets
used near open flame. Use only in a well-ventilated
(Figure C-7, Appendix C)
area.
Hot parts can cause severe burns. Always wear
protective clothing (goggles/shield, gloves, etc.).
5-79
|