Frame Hinge Pin and Frame Assembly. (Sheet 8 of 13)
REMOVAL
Do not remove both upper
shafts at the same time.
at a time, only.
NOTE
and lower
Do one
Repositioning of
surrounding
lines, cables or hoses may be
necessary to accommodate use of
equipment.
44.
Using a bushing removal tool, a 7/16
socket, socket wrench handle and a
7/16 open end wrench, remove bushing
(21).
Install two side pieces of
bushing removal tool in bushing (21)
so the lips of the tool grasp the lower
edge of the bushing (21).
45.
Install the center piece of the
bushing removal tool over the shaft
of the ports-power and between the
two side pieces of the bushing
removal tool.
46.
Install a nut to lock the assembly
together on the ports-power shaft.
Activate the ports-power and push
out bearing (21).
47.
Using a hammer and drift punch,
remove bushing (22).
48.
Remove two bushings (24) from left
and right side of rear frame.
Go to sheet 9