TM 10-3930-643-34
TRANSMISSION TROUBLESHOOTING AND MAINTENANCE. (cent)
6-8.
Scheduling Valve and Control Valve. (Sheet 3 of 4)
REMOVAL (cont)
6.
Using a 9/16 socket and socket
wrench handle, remove
three bolts
(10), washers (11), scheduling valve
(12), six preformed packings (13),
control valve (14) and six preformed
packings (15).
Discard six preformed
packings (13 and 15).
7.
Using a 1 open end wrench,
remove
items 16 thru 19 as an
assembly,
coupling (20) and preformed packing
(21) from scheduling valve (12).
Discard preformed packing (21).
8.
Using 9/16 and
11/16" open end
wrenches, remove cap (16),
coupling
(17) and adapter (18) from tee (19).
CLEANING/INSPECTION
9.
Clean all parts with mild detergent
and wipe dry with clean cloth.
Refer
to paragraph 2-8.
10
Inspect all parts. Refer to para-
graph 2-9.
INSTALLATION
11.
Using 9/16" and 11/16" open end
wrenches,
install adapter
(18),
coupling (17) and cap (16) to tee
(19).
12.
Using a 1" open end wrench,
install
new preformed packing (21), coupling
(20) and items 16 thru 19 as an
assembly to scheduling valve (12).
Go to sheet 4
6-56
|