TM 10-3930-643-34
ELECTRICAL SYSTEM MAINTENANCE.
5-3.
Main Wiring Harness. (Sheet 12 of 15)
INSTALLATION
58.
Connect wire
assembly (41) at
connector to ether start valve.
59.
Apply silicone sealant over entire
connection.
NOTE
The following is a difference
between M10A Forklift models.
60.
Using a 9/16 open end wrench,
install clamp (40), washer (39)
and
bolt (38), from vehicles S/N 2000 and
below.
61.
Install clamp (37), washer (36)
and
bolt (35).
62.
Install clamp (34), washer (33)
and
bolt (32) in front, left side of
engine.
63.
Using a 3/8 open end wrench, connect
two wire assemblies (31) at terminals
to
torque
converter
temperature
sender.
64.
Apply silicone
connection.
sealant over
entire
Go to sheet 13
5-37
|