FRAME AND TOWING ATTACHMENTS TROUBLESHOOTING AND MAINTENANCE. (cont)
11-2.
Roll Over Protective Structure. (S/N 2000 and below) (Sheet 9 of 9)
INSTALLATION
45.
46.
47.
48.
49.
50.
51.
52.
Attach chain and hoist to ROPS
(18) and position ROPS (18) on
top of frame.
Using a 1-1/8 socket, socket wrench
handle and a 1-1/8 open and box end
wrench, install ten washers (17),
bolts (16), washers (15) and nuts
(14) on ROPS (18). Torque ten
nuts (14) to 920 lb-ft.
Using a 11/2 socket, socket wrench
handle and a 1-1/2 open and box end
wrench, install four bolts (13),
washers (12 and 11) and nuts (10).
Torque four nuts (10) to 920 lb-ft.
Using a 9/16 socket, socket wrench
handle and a 9/16 open and box end
wrench, install nine washers (9)
and bolts (8) in floor of operators
compartment.
Torque nine bolts (8)
to 380 lb-ft.
Using a 9/16 socket, socket wrench
handle and a 9/16 open and box end
wrench,
install nine washers (7)
and nuts (6) under operators com-
partment.
Torque nine nuts (6)
to 380 lb-ft.
Remove hoist and chain.
Using hoist and sling, position
ladder (5).
Using a 3/4 socket, socket wrench
handle and a 3/4 box and open end
wrench,
install two washers (4),
bolts (3), washers (2) and new
locknuts (1). Remove hoist and
s l i n g.
NOTE
Return M10A Forklift to original
equipment condition.
TM 10-3930-643-20
END OF TASK
11-11
|