TM  10-3930-638-24&P 4-4.   TRANSMISSION   MAINTENANCE   (cont) b. Converter Housing (cont). STEP LOCATION ITEM ACTION REMARKS REASSEMBLY  (cont) (cont) 23 24 b. SIX screws  (13)  and Install lock washers (14) Tighten to 23-25 pounds foot torque NOTE In the following step, slot in bearing must be downward (oppo- site  splined  end  of  shaft). Turbine a. Bearing  (12) Install Press  using  suitable  size  sleeve shaft hub b. Locating washer (11) Install assembly c. Retaining ring (10) Install d. Piston ring (9) Install Converter Turbine shaft hub Position While spreading ears on retaining ring (7) housing, assembly (8) tap turbine shaft (8) into position. Be rear sure retaining ring (7) is fully engaged in slot of bearing (12) 4 - 1 6 0